Non-conformance report
A non-conformance report (NCR sometimes referred to as a non-conformity report) is a formal document used to identify, record, and address instances where work, materials, or processes do not meet the specified requirements or standards. It serves as a crucial tool for maintaining quality control and ensuring that construction projects comply with contractual, regulatory, and industry standards.
The primary purpose of an NCR is to document any deviation from the agreed standards, specifications, or contractual requirements. It ensures that non-conforming work is identified, assessed, and corrected to prevent recurrence and to maintain the overall quality of the project.
For example, NCRs might be required:
- When materials delivered to the site do not meet the required specifications or are damaged.
- If the work carried out does not meet the quality standards set out in the project specifications.
- If there are deviations from approved construction methods or procedures.
- Breaches of health and safety regulations or practices.
An NCR might include:
- A detailed explanation of the issue, including what was found to be non-compliant.
- The standards, specifications, or drawings that the work should have conformed to.
- Information about where and when the non-conformance was identified.
- The party responsible for the non-conformance.
- Suggested actions to correct the non-conformance.
- Review and approval by relevant parties, such as the project manager, quality control officer, or site engineer.
The NCR is reviewed by the appropriate authority to determine the severity and impact, and actions are proposed and implemented to rectify the non-conformance. The corrective actions are then reviewed to ensure they have been effective in resolving the issue, and the NCR is then formally closed.
NCRs are vital for maintaining high standards of quality on construction projects. They help to manage and mitigate risks associated with non-compliance and provide a record of issues that can be analysed to improve processes and prevent future non-conformances. They ensure that there is a clear record of issues and corrective actions, promoting accountability within the project team and, helping ensure the successful and compliant delivery of construction projects.
[edit] Related articles on Designing Buildings
- Backlog.
- Burn down chart.
- Commissioning.
- De minimis.
- Defects.
- Defects liability period.
- Defects list.
- Defective Premises - Liability and Measure of Damages.
- Defective Premises Act.
- Final certificate.
- Practical completion.
- Punch list.
- Schedule of defects.
- Site inspection.
- Snagging.
- Work-to-complete list.
Featured articles and news
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.






















